Barnhart Crane & Rigging > Project Detail > Wind Turbine Park - Logistics and Erection
 



Wind Turbine Park - Logistics and Erection

80 Wind Turbines in 80 days

BC&R completed all logistics and erection aspects of an extremely aggressive project to meet the needs of the largest wind energy producer in the US. The 80-wind turbine farm northeast of Evanston is Wyoming's largest and can generate up to 144 megawatts. BC&R efficiently and safely transported and erected the 1.8 MW machines on 65m towers in less than three months overcoming the obstacles of inclement weather and the tight erection schedule. BC&R provided seamless execution of the complicated shipments from multiple US ports to mechanical completion on the jobsite.

Project responsibilities included:

Rail and road logistics.

  • Operation of a nacelle preparation yard for installation of small components
  • Design and fabrication of specialty transport devices
  • Preparation of trailers to transport all major equipment to site
  • Transport scheduling, sequencing and travel


Site Erection

  • Specification of site roads and crane pads.
  • Site warehousing for WTG parts and supplies at a central project yard
  • Site transport of completed 110t nacelles to the WTG pads
  • Specification of major equipment strategy to erect WTG units on an accelerated basis
  • Mechanical erection, cleaning, torque and ancillary installation of 80 WTG units
  • Project supervision, document control, procurement and safety management onsite.